Platting

Subdivision plats, the vacation of rights-of-way, utility easements and other related land use processes are handled by the Platting staff.

Utility Easement Vacation Petition

PUBLIC HEARING REQUIRED

Upon receipt of complete application with fees and all required attachments, a public hearing before the Planning Commission will be scheduled. The petition with all required information and attachments must be in the Planning Department at least 30 days prior to the Planning Commission hearing date. By State Statute and Borough Code, the public hearing must be scheduled within 60 days of receipt of a complete application. 

Download Form